BR-0015: Bridge on U.S. 29/U.S. 70 over W. 5th Ave. in Lexington
BR-0015: Bridge on U.S. 29/U.S. 70 over W. 5th Ave. in Lexington
NCDOT is proposing to replace the bridge on U.S. 29 / U.S. 70 over W. 5th Avenue in Davidson County.
Responses to comments and questions received during the public comment period can be viewed here.
Project Overview Video
Project Highlights
NCDOT Project BR-0015 proposes to replace the bridges on U.S. 29 / U.S. 70 over W. 5th Avenue (S.R. 1192) in Lexington. The project will remove the two existing bridges and replace them with one new bridge in their existing location. The proposed bridge will include:
- Two 12-foot travel lanes
- A 12-foot turn lane (onto off ramps) in each direction
- 6-foot paved outside shoulders
- The bridge includes a 22-foot paved median - 10 foot each directon separated by a 2-foot concrete barrier.
The replacement bridge will be constructed using phased construction. Traffic will utilize crossovers constructed with temporary pavement in the existing medians, and 2-way traffic will travel on an existing bridge in stage 1 prior to demolishing the existing bridge in stage 2.
Other associated proposed roadway improvements along U.S. 29 / U.S. 70 will include:
- Pavement resurfacing
- Widening the median paved shoulders to 10 feet with a 2-foot concrete median barrier
- Lengthening the acceleration and deceleration lanes for ramps within the U.S. 29 / U.S. 70 - W. 5th Avenue interchange.
- The existing ramps in the northeast quadrant of the interchange will remain in their current location with some resurfacing. The existing ramps in the northwest quadrant of the interchange at Murphy Drive will be removed.
The existing loop ramp and adjacent ramp in the southwest quadrant of the interchange will be realigned to accommodate an improved 25 mile per hour design speed for the loop ramp and 45 mile per hour design speed for the adjacent ramp.
West 5th Avenue
The project will include improvements for W. 5th Avenue from the ramp terminal intersection west of the bridges to the National Blvd intersection. In this area, W. 5th Avenue will be upgraded to include:
- Two 12-foot travel lanes
- A 12-foot center turn lane
- 4-foot paved shoulders in each direction
- Curb and gutter
- Under the proposed bridge, a minimum 10-foot berm on each side of the road will provide space for a future sidewalk, if needed.
Murphy Drive
The project will include improvements for Murphy Drive from West 5th Avenue to just beyond Forest Rose Drive. In this area, with the removal of the existing exit from U.S. 29/70, the intersection with W. 5th Avenue will be reconstructed and the roadway realigned and reconnected to Murphy Drive just beyond Forest Rose Drive.
The project is state-funded, additional right of way will be necessary, and temporary construction easements will be utilized as needed.
Project Design Map
Click here or on the map image to open the map in a new window for downloading or viewing.
Proposed Typical Sections
U.S. 29 / U.S. 70 - Approaches to Bridge
U.S. 29 / U.S. 70 - Bridge Structure
W. 5th Avenue Typical Section
Murphy Drive Typical Section
Project Funding
| Estimated Amount* |
Right of Way Acquisition | $ 2.7 Million |
Utility Cost | $ 0.4 Million |
Construction Costs | $16.2 Million |
Total Cost | $19.3 Million |
* Estimated costs are preliminary and subject to change
Project Timeline
Milestone | Date* |
Environmental Document | September 2023 |
Begin Right of Way Acquisition | April 2024 |
Begin Construction | June 2025 |
* Schedule is preliminary and subject to change
Project Comments
NCDOT accepts comments throughout all phases of project development.
All comments will be taken into consideration, and carry equal weight, regardless of submittal method.
To submit comments for consideration during the current phase of project development,
please submit before July 14, 2023.
The public is encouraged to leave comments using this webpage, email, or phone number:
Email: US29-70-Lexington@PublicInput.com
Phone Number: 984-205-6615 enter project code 2007
Project Contact
Jennifer Hernandez, PE
NCDOT Project Management Unit
Project Manager
1581 Mail Service Center
Raleigh, NC 27699-1581
Project Contact
Elizabeth Workman
Three Oaks Engineering
Sub-Consultant Project Manager
1730 Varsity Drive #140
Raleigh, NC 27606
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here: https://publicinput.com/NCDOT-Title-VI
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos