Open House Public Meeting

March 5, 2025

5 pm to 7 pm

The Clayton Center

115 East 2nd Street

Clayton

There will be no formal presentation.

This is an open house "drop-in" public meeting.

________________________________________________________________________

Please note, this page is intended to provide information that will be provided at the upcoming public meeting                        and solicit feedback from the public. 

For additional information, please visit the NCDOT webpage: 

 https://www.ncdot.gov/projects/nc-42-widening/Pages/default.aspx

________________________________________________________________________

Project Overview

Thank you for taking the time to provide your input on the N.C. 42 Widening Project. 

The proposed project will widen N.C. 42 (South Lombard Street in Clayton) from a two-lane roadway to a four-lane, median-divided roadway. The project will extend from N.C. 50 to U.S. 70 Business (Clayton Boulevard) but will not include the I-40/N.C. 42 interchange, where widening and other improvements were completed in 2024 as part of a separate NCDOT contract.

NCDOT is currently advancing engineering designs along this N.C. 42 corridor for this proposed project.  The widened roadway will include new bridges over Swift Creek, Little Creek and White Oak Creek.

To facilitate the smooth movement of traffic along this corridor, NCDOT proposes to upgrade numerous intersections, some with innovative designs to help improve traffic flow while minimizing property impacts. Some intersections will remain as traditional ones with traffic signals with such added improvements as dedicated turn lanes, increased turn-lane length, and improved traffic signals.

Other intersections, however, will be converted into reduced conflict intersections, ​which is a general term used by NCDOT to describe several types of designs that can be used to improve safety and traffic flow on a highway.  There are variations to this design, but they all function the same by reducing the number of movements, to improve traffic flow and safety.

The intersections along the NC 42 corridor for this proposed project may include median U-turns, roundabouts, and directional crossovers. . NCDOT has updated the design maps for the March 2025 public meeting to reflect which intersection would be improved by these type of innovative designs.

For additional information about RCIs visit https://www.ncdot.gov/initiatives-policies/Transportation/safety-mobility/reduced-conflict-intersections/Pages/default.aspx.

________________________________________________________________________

Using the tabs above, or the links below this key map, will open the individual map page to view and comment on each map.

 

 

Map 1                         Map 2                           Map 3                          Map 4                         Map 5                         Map 6                          Map 7 

Question title

Please provide any comments or questions you may have regarding the overall project to make improvements to N.C. 42.

Question title

If you would like to be added to our contact list for updates please provide your email.

Project Phase

Cost*

Project Development and Design

$     3.5 Million

Right of Way Acquisition

$   55.9 Million

Utility Relocation

$   10.5 Million

Construction

$ 156.9 Million

Total Cost

$ 226.8 Million

* Costs are estimates and subject to change

Project Schedule

Date*

Environmental Document

Summer 2018

Right of Way Acquisition Begins

Winter 2027

Utility Relocation Begins

January 2027

Project Awarded for Construction

2031

Based on Draft 2026-2032 State Transportation Improvement Program (STIP)

Future dates are subject to change

Comments

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit before March 21, 2025.


The public is encouraged to leave comments using this webpage, email, or phone number:

Email: NC42-Clayton@publicinput.com

Phone Number: 984-205-6615 and enter project code 11141 to leave a message

 

Comments may also be submitted by U.S. Mail to the Project Manager

Russell Broadwell

Project Manager

NCDOT Highway Division 4

PO Box 3165
Wilson, NC 27895