U-6059A: Bridge - Old Greensboro Rd - Winston-Salem
U-6059A: Bridge - Old Greensboro Rd - Winston-Salem
The N.C. Department of Transportation proposes to replace Bridge No. 211 on Old Greensboro Road over the Norfolk Southern Railroad in Winston-Salem.
Interactive Study Map
Project Overview
The N.C. Department of Transportation proposes replacing Bridge No. 211 on Old Greensboro Road over the Norfolk Southern Railroad in Winston-Salem. The project is needed because the bridge was constructed in 1953 and has reached the end of its lifespan.
A new bridge will be constructed immediately north of the existing structure. During construction, traffic will be maintained on the existing bridge to minimize disruption. The proposed bridge will span approximately 139 feet and will include two 12-foot-wide travel lanes, separated by a 6-foot-wide concrete median. Additional width has been incorporated into the design to accommodate a future multi-use path on the north side and a sidewalk on the south side.
The project also includes the realignment of Mountain Street to the west and the construction of a "peanut" roundabout at the intersection of Old Greensboro Road, Myer Lee Road, the realigned Mountain Street, and the U.S. 421 Southbound on and off-ramp.
A "peanut" roundabout is a type of roundabout with a distinctive shape that looks like a peanut with two circular ends connected by a narrow middle section. It is essentially two mini roundabouts joined together, creating an elongated shape resembling a peanut. A peanut roundabout is designed to improve traffic flow at off-set intersections where the junctions are too wide or oddly shaped and where a traditional circular roundabout will not fit or operate efficiently.
The peanut roundabout will be constructed in stages to allow traffic to be maintained on-site throughout construction, minimizing disruption to local traffic.
Project Maps
Click on the map or this link to view a larger version of the map.
For information on how to navigate roundabouts, see the video below:
Typical Section Old Greensboro Rd./Linville Rd.
Typical Section Old Greensboro Rd./Linville Rd. (Bridge over Railroad)
Typical Section (Mountain St.)
Project Funding:
Activity | Estimated Costs* |
Utility Relocation | $ 1.1 Million |
Right-of-Way Acquisition | $ 450,000 |
Construction | $ 12.9 Million |
Total cost | $ 14.5 Million |
*Costs shown are estimates and are subject to change.
Based on currently adopted NCDOT State Transportation Improvement Program.
Project Timeline:
Activity | Anticipated Date* |
Public Outreach | September-October 2025 |
Environmental Document Completion | December 2025 |
Start Right-of-Way Acquisition | 2026 |
| Start Utility Relocation | 2028 |
| Start of Construction | 2028 |
*Future dates subject to change
Project Comments:
NCDOT accepts comments throughout all phases of project development.
All comments will be taken into consideration, and carry equal weight, regardless of submittal method.
Comments for consideration during the current phase of project development
were to be submitted by October 20, 2025.
The public is encouraged to leave comments using this webpage, email, or phone number:
Email: old-greensboro-bridge@publicinput.com
Phone Number: 984-205-6615 and enter project code 12044 to leave a message
Project Contact Information
Connie James
Division Project Manager
NCDOT Division 9
375 Silas Creek Parkway
Winston Salem, NC 27127
Project Contact Information
Chris Anderson
Consultant Project Manager
Wetherill Engineering
15801 Brixham Hill Avenue, Suite 530
Charlotte, NC 28277
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here https://publicinput.com/NCDOT-Title-VI-Form
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos