Project Overview

The N.C. Department of Transportation proposes to construct a bridge on New Hope Church Road (S.R. 2034) over the CSX S-line railroad.  This bridge will replace the existing at-grade crossing.

Project History

This project was studied under the Southeast High-Speed Rail (SEHSR) project. The initial environmental analysis is covered under the Federal Railroad Administration’s 2015 Final Environmental Impact Statement and 2017 Record of Decision. The NCDOT Rail Division is analyzing the changes thereof to the project design and any potential environmental impacts. A public meeting was held for this project in March 2017.

Proposed Design Changes

The 2017 public meeting maps showed New Hope Road and the proposed bridge being shifted approximately 100 feet south of the existing crossing.

Design Change #1:  New Hope Church Road and proposed bridge shifted to existing alignment.

 

On the north side of New Hope Church Road, east of the crossing, the 2017 public meeting maps proposed the extension of the existing shopping center driveway to connect New Hope Church Road.

Design Change #2:  A new driveway access road to the shopping center, through the Quality Oil property, north of New Hope Church Road on east side of crossing, is now proposed.

 

Project Map

Click here or on the map image to open the map in a new window for downloading or viewing.

 

Project Visualizations

 

Aerial view of the proposed project after completion

 

View of the proposed bridge after completion

Typical Section

 

 

Project Funding:

 Activity

 Estimated Costs*

Right-of-Way Acquisition

$ 3,300,000

Construction

$23,700,000

Total Cost

$27,000,000

*Estimated costs are subject to change. Based on currently adopted NCDOT State Transportation Improvement Program.

Project Timeline:

 Activity

Anticipated Date*

Public Meeting

 2017

Environmental document

March 2017

Construction Begins

August 2024

*Future dates subject to change

Project Comments

 

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit below.


The public is encouraged to leave comments using this webpage, email, or phone number:

 

Email: New-Hope-Church-RR-Xing@publicinput.com

Phone Number:  984-205-6615    enter project code 5038

Question title

Would you like to be added to the project email list?

Question title

Do you have any comments or questions regarding the proposed project?

Closed to responses

PROJECT CONTACT INFORMATION 

Gregory Blakeney

NCDOT Rail Project Development Engineer

NCDOT Rail Division

1553 Mail Service Center

Raleigh, NC 27699

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish