U-2530A: N.C. 127 Widening - Hickory
U-2530A: N.C. 127 Widening - Hickory
Widening of N.C. 127 from Huffman Farm Road to Zion Church Road, in Catawba County.
Project Study Area
This map is for reference only and is a representation of the general project area.
Project Updates
The N.C. Department of Transportation will continue to evaluate the potential impacts and avoidance and minimization measures as the project designs are further developed. The project team expects to complete the environmental document, a federal Categorical Exclusion, in the summer of this year.
The N.C. Department of Transportation has completed the environmental studies for this project. The environmental document, a federal Categorical Exclusion (CE) was signed on April 10, 2025. NCDOT will continue to evaluate avoidance and minimization measures as the project progresses through the final design process.
Project Overview
The N.C. Department of Transportation proposes to widen N.C. 127 through the Mountain View area as part of State Transportation Improvement Program (STIP) Project No. U-2530A. The proposed improvements extend from Huffman Farm Road to Zion Church Road, a total project length of 3.1 miles.
The purpose of this project is to improve current traffic conditions as well as accommodate future traffic volumes. Accommodations for bicycles and pedestrians are also being considered in accordance with state and local planning goals and coordination efforts.
Project Highlights
Following the initial Public Meeting in October 2018, the project team developed two alternatives for analysis to address the congestion along N.C. 127. Both alternatives included widening to a 4-lane, median divided roadway with bicycle and pedestrian accommodations. The key difference was the alignment.
To minimize the potential impacts on the community, in June 2019, the project team elected to proceed with the best-fit alignment option to develop preliminary designs. Shortly after, the project was placed on hold as NCDOT dealt with funding challenges and COVID-19.
The project was restarted in June 2023 and the project team further developed preliminary designs which were presented to the public at the March 21, 2024, Public Meeting. Following Public Involvement, the project team continued to field comments and coordinate with local officials, area residents, and other stakeholders to reduce impacts and address concerns. Potential impacts were outlined in the CE and the project moved into final design in May 2025. The project team will continue to refine the project design over the coming months and evaluate avoidance and minimization measures.
Proposed Typical Sections
N.C. 127 Typical Section with Full Median
N.C. 127 Typical Section with Left-Turn Lane
Highlights of the Proposal include:
Two lanes in each direction with a grass or paved median and dedicated turn lanes at key locations
All existing signals will remain
The following locations will remain full-movement intersections:
Huffman Farm Road | Bethel Church Road |
Village Circle | Moss Farm Road |
Dwayne Starnes Road | Westover Road |
Valley Field Road | Plaza Drive |
Mountain Grove Road | Zion Church Road |
- Dedicated northbound left-turn lanes will be provided from N.C. 127 to:
Moss Farm Road
Westover Road
Fleetwood Road
S. Center Street
Dedicated southbound left-turn lanes will be provided from N.C. 127 to:
Zion Church Drive
Medical Park Drive
Plaza Drive
Westover Road
Woodridge Drive
Mountain View Centre entrance (next to El Sarape)
Bethel Church Road
Old Farm Drive
Valley Field Drive
Huffman Farm Road
Left turns from other existing side streets and driveways will be redirected
U-Turn bulbs will be added at:
Dwayne Starnes Road
Pinewinds Drive
Mountain Grove Road
Bethel Church Road
U-turns are also permitted at signalized intersections
Bethel Church Road will be realigned with turn lane improvements
Through coordination with city and county planning officials and consistent with local plans for the area, buffered bicycle and pedestrian accommodations are being provided:
5' sidewalk along the west/north side of N.C. 127, separated from traffic by a 4-foot planted median
10' multi-use path along the east/south side of N.C. 127, separated from traffic by a 4-foot planted median
Pedestrian crossings will be provided at signalized intersections
Project History
The N.C. 127 widening project was first identified in 2002 as part of the Mountain View Small Area Plan with recommendations to widen N.C. 127 to a median divided, 4-lane roadway with bicycle and pedestrian facilities. The project was then later included in the Catawba County Thoroughfare Plan in 2007 and the Greater Hickory Metropolitan Planning Organization Long Range Transportation Plan in 2013.
NCDOT first prioritized the project based on the Strategic Transportation Investments Law and added it to the 2016-2025 STIP. Since this time, the project has maintained its importance as a key corridor for improvements and is most recently documented in the 2024-2033 STIP.
Project Funding
Project Phase | Estimated Amount* |
Property Acquisition | $ 25.0 million |
Utility Relocation | $ 3.9 million |
Construction Costs | $ 64.4 million |
Total Cost | $ 93.3 million |
* Estimated costs are preliminary and subject to change
Project Timeline
Milestone | Date* |
Complete Environmental Document | Spring 2024 |
Right of Way Acquisition Begins | Summer 2025 |
Construction Begins | Fall 2026 |
* Future dates are preliminary and subject to change
Project Comments
NCDOT accepts comments throughout all phases of project development.
All comments will be taken into consideration, and carry equal weight, regardless of submittal method.
The public is encouraged to leave comments using this webpage, email, or phone number:
Email: NC-127-Widening@PublicInput.com
Phone Number: 984-205-6615 enter project code 2815
___________________________________
Responses to comments received during the public comment period can be viewed here.
A summary for public meeting #2 can be viewed here.
Project Contact
Bryan Sowell, P.E.
NCDOT Division 12
Project Development Engineer
P.O. Box 47
Shelby, NC 28151
Project Contact
Jenny Noonkester, AICP
RS&H
Consultant Project Manager
1520 South Boulevard, Suite 200
Charlotte, NC 28203
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here: https://publicinput.com/NCDOT-Title-VI
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos