R-2527: N.C. 24/27 Improvements

R-2527: N.C. 24/27 Improvements

 NCDOT proposes to improve the Uwharrie Trailhead Parking Lot on N.C. 24/27 east of River Road in Montgomery County. NCDOT needs your input on this proposed improvement as it will involve realignment of a portion of the trail in the vicinity of the parking lot.

Vicinity Map:

 

Image: Project parking lot and trail improvements

Project Overview:

The N.C. Department of Transportation plans to make improvements to N.C. 24/27 from N.C. 73 to the Troy Bypass. The project would widen existing N.C. 24/27 to a four-lane divided roadway.

As part of the proposed improvements NCDOT, in coordination with the United States Forest Service, has committed to extend the existing N.C. 24/27 trailhead parking lot.  Construction of the parking lot will require a portion of the Uwharrie Recreational Walking Trail to be realigned. Impacts to the walking trail are expected to be minimal and will not adversely affect the activities, features and attributes that qualify the soil trail’s protection under the U.S. Department of Transportation’s Section 4(f) law. 

Project Highlights:

Project R-2527 is approximately 8.25 miles long and involves widening N.C. 24/27 in Montgomery County from a two-lane facility to a four-lane divided facility with a 46-foot depressed grass median and 10-foot outside shoulders. The proposed design speed will be 60 mph.  

It is anticipated that 150 to 250 feet of right-of-way will be required to accommodate the proposed improvements. The project will be designed with partial control of access. All intersecting roadways will cross the highway at grade and no grade separations or interchanges are proposed. The project also includes the replacement of a rail line crossing over N.C. 24/27. The track is owned by the Norfolk Southern Railway and is leased to Aberdeen Carolinas and Western Railway.  Construction on Project R-2527 is anticipated to begin in 2023.

Map of Proposed Improvements:

Image: Uwharrie walking trail

Project Funding

Activity

Estimated Amount*

 

 

Right-of-Way
Acquisition

$626,000

 

 

Utilities Relocation

$1,600,000

 

 

Construction Cost

$131,500,000

 

 

Total Cost

$133,726,000

 

 

 

* Estimated costs are subject to change. Based on NCDOT STIP.

Project Timeline

Milestone

Date*

 

 

Public Meeting

June 2012

 

 

Complete Environmental Document

April 2017

 

 

Utility Relocation

Begins

November 2024

 

 

Right-of-Way Acquisition

Begins

February 2019

 

 

Begin Construction

September 2027

 

 

* Future dates are preliminary and subject to change

Comments:

NCDOT accepts comments throughout all planning, design and construction phases of project development.

All comments will be taken into consideration, and carry equal weight, regardless of submittal method. 

 

Email the comment or question to
uwharriewalkingtrail@Publicinput.com

Or

 Phone Number: (984) 205-6615   Code: 10012

 

Contact Information

Would you like to be added to the project email list for updates or other information?

Do you have any questions regarding the proposed project?

Closed for Comments

Project Contact Information:

Andrew Folz, P.E.

NCDOT Project Management Unit

Senior Project Manager

1585 Mail Service Center

Raleigh, NC  27699-1585

uwharriewalkingtrail@Publicinput.com

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI-Form

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  


Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

     
Right of way Acquisition Process Videos

English                                                                     Spanish

 

 

 

Page last updated: August 24, 2026

ADA Compliance Checked