U-5717: U.S. 15-501 at Garrett Road
U-5717: U.S. 15-501 at Garrett Road
Preliminary Engineering Activities for this project
have been suspended.
PROJECT DESCRIPTION
The N.C. Department of Transportation is proposing to improve U.S. 15-501 (Durham Chapel Hill Boulevard) and Garrett Road (S.R. 1116), within the City of Durham. This project will upgrade the at-grade intersection to an interchange. The purpose of the project is to reduce congestion and improve traffic operations at the intersection.
Vicinity Map:
PROJECT STATUS
Three interchange designs were developed for the project:
Alternative A is a tight diamond that would carry U.S. 15-501 over Garrett Road.
Alternative B is a tight diamond that would carry Garrett Road over U.S. 15-501.
Alternative C is an interchange with roundabouts at the ramp terminals of U.S. 15-501 and Garrett Road.
A public meeting was held on October 9, 2017 to present the alternatives and get feedback from the public.
Based on the public comments received and a preliminary evaluation of impacts and costs,
NCDOT selected Alternative A for detailed study in the project’s environmental document.
This Alternative is a 'Tight Diamond' interchange that would carry U.S. 15-501 over Garrett Road.
Alternative A causes the least impact to the Durham-Orange Light Rail Transit project,
the least impact to properties at the intersection, and
meets the purpose and need of the proposed project.
NCDOT considers many things when making decisions on transportation projects.
On this project, items investigated include:
property impacts, cost, traffic operations, and impacts to the Durham-Orange Light Rail Transit Project (D-O LRT).
PROJECT HISTORY
The Durham Chapel Hill Carrboro MPO Comprehensive Transportation Plan articulates a desire for U.S. 15-501 between I-40 and U.S. 15-501 Bypass to operate at Level of Service (LOS) D or better. The projected traffic volume for 2040 is anticipated to exceed the capacity of the roadway and operate at level of service (LOS) F.
The intersection of U.S. 15-501 and Garrett Road is currently (2016) operating at LOS D and is projected to operate at LOS F in 2040. On average, drivers experience 45.1 seconds of delay during the morning peak and 46.6 seconds of delay during the afternoon peak. This delay is projected increase to 202.2 seconds of delay during the morning peak and 209.5 seconds of delay during the afternoon peak by 2040.
Level of Service (LOS)
Project Timeline
Milestone | Date* |
Public Meeting | October 9, 2017 |
Environmental Document Signed | November 27, 2018 |
Right of Way Date | April 21, 2019 |
Construction | FY 2026 |
* Future Dates are subject to change
Project Funding
This project is listed as Project U-5717 in the FY 2020-2029 STIP and is funded for $43.4 million.
Task | Estimated Cost* |
Right of Way Acquisition, Utilities, and prior costs | $ 20,413,800 |
Construction Costs | $ 32,000,000 |
Total Cost | $ 52,413,000 |
* Cost as shown in Currently Adopted STIP and are subject to change
PUBLIC INVOLVEMENT
The NCDOT project team will review all feedback – regardless of how it is submitted (online, phone, email, or letter) – and explore options to incorporate and address concerns where and when feasible. NCDOT will continue to develop the project and present progress throughout the planning stage.
PUBLIC MEETINGS
NCDOT conducted an open-house public meeting to present maps of the three alternatives being studied and receive feedback on October 9, 2017.
PROJECT MAPS
Please Click on the links below to view or download Maps and Visualizations of the project alternatives.
PREFERRED ALTERNATIVE:
Alternative A (Tight Diamond Interchange - U.S. 15-501 Over Garrett Road)
Visualization of Alternative A
Other Alternatives considered:
Alternative B (Tight Diamond Interchange - Garrett Road Over U.S. 15-501)
Visualization of Alternative B
Alternative C (Teardrop Roundabout)
Visualization of Alternative C
PROJECT CONTACT INFORMATION
John Braxton |
NCDOT Project Manager |
NCDOT Division 5 |
1573 Mail Service Center |
Raleigh, NC 27699-1582 |
919-707-6219 |
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos