Project Overview:

The N.C. department of Transportation proposes to replace the Bridge on Lindsey Bridge Road over the Dan River in Rockingham County. 

Project Highlights: 

The project proposes to replace the Bridge on Lindsey Bridge Road on new location to the east of its existing location. Construction of the bridge, scheduled to begin in February 2023, is anticipated to take up to 24 months. Lindsey Bridge Road is anticipated to be closed at the project location for up to one month during that timeframe to construct the tie‑in to the existing roadway on the north side of the bridge.

  • During the anticipated one-month closure of the bridge, traffic will be detoured offsite. Traffic will be detoured onto Rierson Road (S.R. 1143), Ellisboro Road (S.R. 1110), Mineral Springs Road (S.R. 1145), and U.S. Highway 311 for approximately eight (8) miles.
  • The proposed bridge will be approximately 543 feet long and 34 feet wide. The proposed bridge typical cross section includes two 11-foot travel lanes and 6-foot paved shoulders on the outside travel lanes.
  • The existing bridge, built in 1957, is considered structurally deficient. This means the bridge, while safe, is in relatively poor condition and/or has insufficient load-carrying capacity, which may be due to the original design or to deterioration.

Public Input:

Information will be provided to the public in a virtual format on this website. The public comment period ended for this portion of development on April 6, 2022.

Please click here (or on the map below) to view or download the current project map.

 

 

 

Project Visualizations of bridge replacement on Lindsey Bridge Road over the Dan River

 

 

 

 

 

 

Bridge Typical Section

 

Project Funding:                                           

 

 Activity

 Estimated Amount*

 Property Acqusition

$ 610,000

 Construction Costs$ 6,100,000

 Prior Years Costs

 $ 950,000 

  Total Cost

$ 7,660,000

* As shown in the currently adopted State Transporation Improvement Program - Subject to change

Project Timeline:

 

 

Milestone

    Date*

 Public Outreach

March 2022

Environmental DocumentApril 2022

 Right of Way Acquisition

 May 2022

 Construction Begins 

February 2023

 As shown in the currently adopted State Transporation Improvement Program - Subject to change

Comments:

NCDOT accepts comments throughout all planning, design and construction phases of project development.

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development, please submit before Month, day, year.  

You may leave a comment or question below

Or

Email the comment or question to LindseyBridgeRd-Madison@PublicInput.com

Or

 Phone Number: (855) 925-2801 Code: 9020

 

Question title

Would you like to be added to the project email list for updates or other information?

Question title

Do you have any comments or questions regarding the proposed project?

Project Contact Information:

Tim Powers, PE

NCDOT Highway Division 7

 Division  Bridge Program Manager

1584 Yanceyville Street

Greensboro, NC 27415

 

Project Consultant Information:

Aileen Mayhew, PE

Mott MacDonald

Project Manager 

7621 Purfoy Road, Suite 115

Fuquay-Varina, NC 27526

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right-of-way acquisition and answers questions about the process.  

 

Relocation Assistance Brochure                                       Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure                   Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions