Open House Public Meeting

_____________________________________________

 January 29, 2025

Boonville Elementary School

232 E Main St.

Boonville, NC 27011

 5:00 p.m. to 7:00 p.m.

No formal presentation will be made

_____________________________________________

Interactive Study Area Map

Interactive Study Area Map

Project Overview

The purpose of the project is to improve mobility and safety. N.C. 67 is a two-lane highway with narrow travel lanes and no shoulders which does not meet current design standards. N.C. 67 serves as a connector route between I-77 and Winston-Salem. Existing and future traffic on N.C. 67 is not expected to exceed capacity but the corridor was identified as a candidate for upgrading to current NCDOT design standards.  This facility is recommended to have 12-foot lanes with paved shoulders in order to improve mobility and safety.

Project R-5914 is included in the NCDOT’s currently adopted 2024-2033 State Transportation Improvement Program (STIP) with right-of-way acquisition programmed in fiscal year (FY) 2026 and construction programmed in FY 2028. Please note this schedule is subject to change. NCDOT is preparing an environmental document, and a Categorical Exclusion (CE).

Improvements along N.C. 67 include:

  • 3-lane road (two thru-lanes, one in each direction and a center turn lane) with curb and gutter and sidewalks on each side of the roadway from Mill Street to River Road 

  • 2-lane road with 5-ft paved shoulders from River Road to the Town of East Bend

  • Left turn lanes on N.C. 67 eastbound and westbound at the intersection of Nebo Road/Smithtown Road

  • Several intersections will be realigned to improve roadway angle

  • West Main Street – intersection to be reconfigured

Not sure which map page you want to look at first?

 Clicking on the map below will open it in a new window where you can view the maps by clicking on the individual map sections shown along the corridor.

Individual maps can also be viewed by clicking on the pictures below.

Project Maps

R-5914 Map 1

U.S. 601 to East of Robbins Ln.

 

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 1.

R-5914 Map 2

Ridge St to Weldon Rd.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 2.

R-5914 Map 3

Stinson Rd to East of HD Dr.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 3.

R-5914 Map 4

Rockford Rd to West of Pendry Dr.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 4.

R-5914 Map 5

West of Pendry Rd to Mickles Ln.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 5.

R-5914 Map 6

West of Maye House Ln to Creekview Dr.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 6.

R-5914 Map 7

East of Creekview Dr to East of Arzy Rd.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 7.

R-5914 Map 8

West of Fall Creek School Rd to East of Heritage Dr.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 8.

R-5914 Map 9

Samantha Ln to East of Mill Hill Rd.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 9.

R-5914 Map 10

Meadow View Rd- East of Pride's Rd.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 10.

R-5914 Map 11

Pride's Rd to West Main St.

Question title

Please provide any comments or questions you may have regarding proposed improvements shown on Map 11.

Typical Section

N.C. 67  between Mill Street and River Road

(Boonesville Area) 

Typical Section

N.C. 67 between River Road and West Main Street

(From Boonesville to East End)

 

  

 

Project Funding:

 

 Activity

 Costs*

 Right Of Way Acquisition

 $    24.8 Million   

 Utility Relocation 

$    14.8 Million   

 Construction 

$    92.1 Million   

 Total Cost

 $ 131.7 Million  

        *costs are subject to change. 

Project Timeline:

 

Milestone

    Date*

Public Meeting 

January 2025 

Environmental Document

April 2025 

Right-of-Way Acquisition BeginsMarch 2026 

Construction Begins

March 2029 

* Future dates subject to change. 

Comments:

 

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit by Feb 28, 2025


The public is encouraged to leave comments using this webpage, email, or phone number:

Email: 

NC67-Boonville-EastBend@publicinput.com

 Phone Number:   984-205-6615  enter project code: 7516 to leave a message. 

Question title

Please provide any comments or questions you have regarding the overall proposed project.

Question title

Would you like to be added to the project email list?

PROJECT CONTACT INFORMATION 

Daniel Adams

Division Project Team Lead

NCDOT Highway Division 11

P.O. Box 250

North Wilkesboro, N.C. 28659-0250

PROJECT CONTACT INFORMATION 

Jenny Noonkester

Consultant Project Manager

RS&H

1520 South Blvd, Suite 200

Charlotte, N.C. 28203

RESOURCES FOR PROPERTY OWNERS 

 

Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish

  

 

 

 

 

 

 

 

 

 

 

 

 

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI