Skip Navigation

U-5753: Wayside Rd

U-5753: Wayside Rd

This project proposes to widen Wayside Road (S.R. 1305) from U.S. 401 to Plank Road and widen Lindsay Road (S.R. 1418) from Rockfish Road (S.R. 1406) to U.S. 401 to a median-divided boulevard.

Interactive Vicinity Map:

 

PROJECT DESCRIPTION

This project proposes to widen S.R. 1305 (Wayside Road) from U.S. 401 to Plank Road and widen S.R. 1418 (Lindsay Road) from S.R. 1406 (Rockfish Road) to U.S. 401 to a median-divided boulevard.  The proposed project includes U-5858 with the purpose to improve traffic safety and reduce congestion in the area south of Fort Bragg as a part of a series of projects between Fort Bragg and the community of Rockfish.

 

Preferred Alternative Selected

State Transportation Improvement Program Project No. U-5753

Wayside Road Widening Between Plank Road and U.S. 401

 

The N.C. Department of Transportation has selected the preferred alternative for State Transportation Improvement Program (STIP) Project No. U-5753 along Wayside Road (S.R. 1305) in Hoke County. 

The proposed project will improve traffic safety and reduce congestion in the area south of Fort Bragg as part of a series of roadway improvements between Fort Bragg and the community of Rockfish.


Concept 1 has been selected as the preferred alternative. 

Concept 1 will widen Wayside Road to a 4-lane median divided boulevard with shoulders, and includes: 

Realignment of Wayside Road to the east of its current location to meet Plank Road as a “T” intersection
Realignment of Wayside Road at U.S. 401 to meet Lindsay Road as a grade separated interchange over U.S. 401.


Concept 1 was selected after careful review of the environmental impacts associated with each of the project options under consideration, as well as comments received from citizens during the public comment period. 

The N.C. Department of Transportation issued an environmental document for the project in December 2021.  The document combines the U-5753 project with STIP Project U-5858 (Lindsay Road).

For additional project information, contact Andrew Folz, NCDOT Project Manager, at 1548 Mail Service Center, Raleigh, NC. 27669-1548, via telephone at (919) 707-6341 or by email at afolz@ncdot.gov.

PROJECT HIGHLIGHTS

The project is following a study process outlined by the National Environmental Policy Act, a law that requires NCDOT to study and document the environmental effects of the proposed project.  Two design concepts with options have been developed for public review and comment. 

Design Concept 1 would widen Wayside Road to a median divided boulevard with shoulders

Wayside Road would be realigned at U.S. 401 to meet Lindsay Road as a grade separated interchange over U.S. 401 

Design Concept 2 would widen Wayside Road to a median divided boulevard with curb and gutter 

Wayside Road would be realigned at U.S. 401 to meet Lindsay Road as a grade separated interchange over U.S. 401   

 

 

Design Concept 1

  • Widen Wayside Road to a median divided boulevard with shoulders 

  • Wayside Road would be realigned at U.S. 401 to meet Lindsay Road as a grade separated interchange over U.S. 401 

​typical road section

Design Concept 2

  • Widen Wayside Road to a median divided boulevard with curb and gutter

  • Wayside Road would be realigned at U.S. 401 to meet Lindsay Road as a grade separated interchange over U.S. 401 

​typical road section

After Reviewing the information provided, do you prefer one option over the other?

I prefer Concept 1: Shoulder section
I prefer concept 2: Curb and Gutter section
I have no preference
Closed to responses

Public Involvement

Public Meeting

A public meeting was held on April 23, 2019 in Rockfish to obtain stakeholder and public input regarding the project's design.  

        

 

Public Meeting Maps:

 

Project Funding

Activity

Estimated Amount*

 

 

Right-of-Way
Acquisition

$42,050,000

 

 

Utilities Relocation

$385,000

 

 

Construction Cost

$62,100,000

 

 

Total Cost

$104,535,000

 

 

* Estimated costs are subject to change. Based on NCDOT STIP.

 

 

Project Timeline

Milestone

Date*

 

 

Public Meeting

April 2019

 

 

Complete Environmental Document

December 2021

 

 

Utility Relocation

Begins

June 2024

 

 

Right-of-Way Acquisition

Begins

June 2022

 

 

Begin Construction

February 2027

 

 

* Future dates are preliminary and subject to change

 

COMMENTS/QUESTIONS

 

Comments may be submitted below, via phone, email (wayside-rd@publicinput.com), or U.S. Mail to the Project Manager listed above, or at any meeting. 

All comments received carry equal weight, regardless of submission method. 

All comments will be reviewed and suggestions/recommendations incorporated into designs where feasible.  

PROJECT CONTACT INFORMATION 

Andrew Folz

Senior Project Manager

NCDOT - Project Management Unit

1595 Mail Service Center

Raleigh, NC  27699-1595

wayside-rd@publicinput.com

984-205-6615   Project Code 3739

 

Contact Information

Would you like to be added to the U-5753 (Wayside Road project) USPS or email list? (Remember, if you wish to receive updates on all 5 projects, please sign up on the main page.)

Is there a question or comment that you would like to provide to the project team?

Closed for Comments

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here https://publicinput.com/NCDOT-Title-VI-Form

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

BACK TO MAIN ROCKFISH AREA PROJECTS PAGE

Page last updated: August 25, 2026