Preliminary Engineering Activities for this project
have been suspended
The NC Department of Transportation is proposing to construct a roundabout at the intersection of N.C. 710 and Deep Branch Road (S.R. 1339) in Robeson County.
Both N.C. 710 and Deep Branch Road are two lane roads with a 55 mph speed limit that currently intersect under signal control. Left turn lanes are provided on each approach and right turn lanes are provided on the N.C. 710 approaches. There is a pattern of frontal impact crashes due to red light violations and left turn crashes due to vehicles failing to yield. Data indicates that this location does not meet the requirements for adding left turn phasing to the existing signal.
Based on review of this location, it has been determined that this intersection is a good candidate for conversion to a roundabout.
Vicinity Map:
Purpose and Need:
STIP Project W-5706N is located at the intersection of NC 710 and S.R. 1339 (Deep Branch Road) in Robeson County, NC. Both roads at this intersection have 55 mph speed limits and this intersection is currently signalized; however, there is a pattern of frontal impact crashes due to red light violations. There have been 33 crashes here in the past 5 years.
STIP project W-5706N involves constructing a roundabout at the intersection of N.C. 710 and Deep Branch Road to control traffic flow and improve safety at the intersection.
Public Involvement
Public Meetings
A public meeting was held on July 16, 2019 in Pembroke, NC to obtain stakeholder and public input regarding the project's design.
Date: | July 16, 2019 |
Location: | UNC Pembroke University Center Annex 239 North Odun Pembroke, NC 28372 |
Time: | 5-7 p.m. |
Public Meeting Map from Deep Branch Road to N.C. 710
Project Funding
This project is listed as Project W-5706N in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $2 million.
| Estimated Amount* |
Property Acquisition | $ 215,000 |
Construction | $ 1,375,000 |
Total Cost | $ 1,590,000 |
* Estimated costs are subject to change. Based on NCDOT STIP.
Project Timeline
Milestone | Date* |
Public Meeting | July 16, 2019 |
Planning Document | October 2019 |
Right of Way Acquisition | November 2019 |
Construction Begins | May 2024 |
* Future dates are preliminary and subject to change
PROJECT CONTACT INFORMATION
Jason Hatfield
Division Project Manager
NCDOT Division Highway 6
P.O. Box 1150
Fayetteville, NC 28302
910-364-0603
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.