SM-5708C&D - US-15-501-Pinehurst
SM-5708C&D - US-15-501-Pinehurst
Improvements to the Intersections of U.S. 15-501 at Memorial Drive and Page Road in Moore County
Vicinity Map
Responses to questions received during the public comment period can be viewed or downloaded here.
Project Overview:
NCDOT is proposing to add right turn lanes at the U.S. 15-501 and Memorial Drive intersection and realign Page Road at 15-501 with a new traffic signal. The purpose of the project is to increase mobility in these locations and reduce accidents.
SM-5708C: Construct an eastbound right turn lane on Memorial Drive. Construct southbound right turn lane on U.S. 15-501 at Memorial Dr.
SM-5708D: Realign the Page Road intersection with U.S. 15-501. Install of a new traffic signal.
These are Strategic Prioritization Process (SPOT*) mobility projects that are needed due to traffic volumes and safety concerns. There is a history of accidents at the current Page Road intersection.
* SPOT (Strategic Prioritization Process) is the methodology that NCDOT uses to develop the State Transportation Improvement Program (STIP). The process involves scoring all roadway, public transportation, bicycle, pedestrian, rail, and aviation projects on a number of criteria.
Public Input:
Due to pandemic restrictions, NCDOT has suspended in-person meetings until further notice. Information will be provided to the public in a virtual format. The public is encouraged to provide comments or share their thoughts regarding the project.
The comment period for this phase of project development closed on Feb. 2, 2022
Project Map:
Open or download a copy of the public meeting map of projects SM-5708C and D click here
Typical Sections
Project Funding: SM-5708C
This project is listed in the STIP as Project SM-5708C is funded for $ 484,000 Thousand.
Activity | Estimated Cost* |
Project Development & Design | $ 33,000 |
ROW / Utilities Costs | $ 60,000 |
Construction Costs | $ 391,000 |
Total Cost | $ 484,000 |
*Estimated costs are subject to change.
Project Timeline: SM-5708C
The current project timeline is shown below.
Milestone | Date* |
Public comment | Jan 2022 |
Right of Way Acquisition | May 2022 |
Utility Relocation begins | Nov 2022 |
Construction Begins | Spring 2023 |
*Future dates are subject to change.
Project Funding: SM-5708D
This project is listed in the STIP as Project SM-5708D is funded for $ 750,000 Thousand.
Activity | Estimated Cost* |
Project Development & Design | $ 67,000 |
Property Acquisition | $ 100,000 |
Construction Costs | $ 583,000 |
Total Cost | $ 750,000 |
*Estimated costs are subject to change.
Project Timeline: SM-5708D
The current project timeline is shown below.
Milestone | Date* |
Public Comment | Jan 2022 |
Right of Way Acquisition | May 2022 |
Utility Relocation Begins | Nov 2022 |
Construction Begins | Spring 2023 |
*Future dates are subject to change.
Comments:
All comments will be taken into consideration, and carry equal weight, regardless of submittal method
Project Contact Information:
Michael Ricketts
NCDOT Highway Division 8
Project Manager
121 DOT Drive
Carthage, NC 28327
(855) 925-2801 Code 8911
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos