Project Cost and Timeline

 

 

MilestoneAlternative 1Alternative 2
Utilities  $         1,500,000$                      0
Property Acquisition  $         3,200,000$         4,300,000
Construction Costs  $         7,700,000$         7,700,000
Total Cost  $       12,400,000$       12,000,000

* Estimated Costs are subject to change

 

Milestone       Date*
Public meeting       August 24, 2017  
NCDOT Recommended Alternative             November 2017  
Right of Way Plans Complete           Summer 2018  
Right-of-way Acquisition           Summer 2018  
Construction                   Fall 2021  

* Future Dates are subject to change 

 
 

PUBLIC INVOLVEMENT

PUBLIC MEETING 

NCDOT conducted a public meeting to inform the public of the proposed project and to receive feedback. The meeting was held on August 24, 2017 and comments were received and reviewed following the close of the comment period on September 27, 2017.  

Information on the project was also presented at the Raleigh Area Projects Meeting held at the McKimmon Center in Raleigh on November 8, 2017.

 


PUBLIC MEETING MAPS

The Map presented at the October 16, 2018 meeting can be viewed using the link below: 

https://www.ncdot.gov/news/public-meetings/Documents/U-5826_rdy_phm_09_28_18.pdf

PROJECT CONTACT INFORMATION

Ben Upshaw, PE 
Project Delivery Team Lead 
NCDOT Division 5 
2612 Duke Street 

Durham, NC  27704

 

Email:   

[email protected]
 

 

Resources for Local Property Owners


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.

 

Relocation Assistance Brochure                                  Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure              Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions