Project Overview

The N.C. Department of Transportation is proposing to realign the intersections of Wiggins Road and N.C. 150 and the western intersection of N.C. 150 and N.C. 152 in Mooresville.  The proposed project is the combination of two separate projects but because of their proximity to each other they are being planned, designed, and constructed as one project.

  •  U-5780 proposes to realign the intersection of Wiggins Road and N.C. 150. This realignment will include left turn lanes from N.C. 150 onto Wiggins Road, a right turn lane from eastbound N.C. 150 onto Wiggins Road and signalization.
  • W-5601U proposes to realign N.C. 152 to intersect N.C. 150 at a better angle. The intersection will be signalized with a left turn lane from N.C. 150 onto N.C. 152.

The purpose of this project is to increase safety and traffic capacity along this segment of N.C. 150 and N.C. 150/ N.C. 152.

 

Project Map

U-5780 Project Map

Step 1

Do you have any comments or questions regarding the proposed project?

Closed for Comments
Contact Information

Would you like to be added to the project email list for updates or other information?

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here: https://publicinput.com/ncdot-title-vi-form

 

RESOURCES FOR PROPERTY OWNERS 
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road

project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right

of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of Way Acquisition Process Videos

English                                                                     Spanish

  

 

 

Page Last Updated- May 6 2026

ADA Compliant 

Project Schedule

Based on currently adopted State Transportation Improvement Program (STIP) and subject to change

April 2019 - Environmental Document Signed
June 2019 - Right of Way Plans Complete
August 2021 - Right of Way Acquisition
Summer 2023 - Final Plans Complete
December 2024 - Construction Begins