Project Funding

 This project is listed as Project U-5746 in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $16.555 million.

 

 

 Estimated Amount*

  Right-Of-Way Acquisition

 $  13,266,000

  Utilities

 $    2,313,000

  Construction Cost

 $    3,800,000

  Total Cost 

 $  19,379,000

* Estimated costs are subject to change. Based on NCDOT STIP.

Project Timeline

  Milestone

  Date*

  Environmental Documentation

 September 2018

  Preliminary Design Complete

Fall 2018

  Right-Of-Way Acquisition Begins

  January 2020

  Construction Begins

August 2021

* Future dates are preliminary and subject to change

PROJECT CONTACT INFORMATION 

     

John Braxton                                          Jeremy Potter, PE

    Project Manager                                                  Consultant Project Manager 

 NCDOT Division 5 - Project Delivery                                                       HDR                                    
 [email protected]                                                 [email protected]   
  919-707-6219                                                                 919-232-6669           

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

 

Relocation Assistance Brochure                                                 Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure                             Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions