W-5706L - Old Stage Rd and Sheriff Johnson Road - Harnett
W-5706L - Old Stage Rd and Sheriff Johnson Road - Harnett
The North Carolina Department of Transportation proposes to construct roundabouts at the intersection of Old Stage Road and Sheriff Johnson Road and the intersection of N.C. 27 / Old Stage Road / Leslie Campbell Avenue.
Vicinity and Detour Map:
Interactive Study Area Map:
Map is for informational purposes only and reflects the approximate boundaries of the area in which environmental studies for the project will be conducted.
Project Overview
N.C. Department of Transportation proposes to construct roundabouts at the Old Stage Road (S.R. 1006) / Sheriff Johnson Road (S.R. 1516) intersection and the N.C. 27 / Old Stage Road (S.R. 1006) / Leslie Campbell Avenue (S.R. 2084) intersection. Pavement removal is proposed at the N.C. 27 East / Sheriff Johnson Road (S.R. 1516) intersection.
Project Highlights
Public Involvement
Public Meetings
Due to Covid 19, NCDOT has suspended in-person meetings. Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposed map below.
Comments may be submitted below, via email to OldStageRd-Harnett@PublicInput.com or by calling 512-580-8850 and entering project code 8739 .
The comment period for this project closed on July 23, 2021.
Public Meeting Map:
A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.
Roundabouts in North Carolina
Project Funding:
This project is listed as Project W-5706L in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $ 2.5 million. Cost estimates have been prepared and are shown below.
Activity | Estimated Costs* |
Project Development & Design | $ 240,000 |
Property Acquisition & Utilities | $ 325,000 |
Construction Cost | $ 1,939,000 |
Total Cost | $ 2,504,000 |
Estimated costs are subject to change. Based on currently adopted NCDOT STIP.
Project Timeline:
Milestone | Date* |
Public Outreach | July 2021 |
Final Environmental Document | July 2021 |
Right-of-Way Acquisition Begins | Oct. 2021 |
Construction Begins | Dec. 2022 |
* Future dates subject to change.