HL-0008D: Holly Springs Rd-Sunset Lake Rd
HL-0008D: Holly Springs Rd-Sunset Lake Rd
The N.C. Department of Transportation proposes to widen Sunset Lake Road (S.R. 1301) between Holly Springs Road (S.R. 1152) and Lockley Road (S.R. 3933) in Holly Springs.
Interactive Project Study Area Map:
Project Overview
STIP Project HL-0008D involves widening Sunset Lake Road (S.R. 1301) to four lanes with a median between Holly Springs Road and Lockley Road. A sidewalk is proposed on the west side and a multi-use path is proposed on the east side of Sunset Lake Road within the project limits.
This project page serves as the official source for verified information about construction activities, traffic impacts, schedule updates, and project announcements. Residents, businesses, and travelers are encouraged to sign up through PublicInput.com for project updates by email and/or text message and to check this page for current project information. Project notifications will also be shared through Nextdoor, when appropriate, to help reach nearby communities.
Stay Informed
This project page serves as the official source for verified information about construction activities, traffic impacts, schedule updates, and project announcements. Residents, businesses, and travelers are encouraged to sign up through PublicInput.com for project updates by email and/or text message and to check this page for current project information. Project notifications will also be shared through Nextdoor, when appropriate, to help reach nearby communities.
Project Email: HollySprings-SunsetLake@publicinput.com
Project Hotline: 984-205-6615 enter code 9287 to leave a message
Current Construction Status
Current Activities
Current and upcoming work activities may be posted here as construction progresses and as information becomes available and is confirmed. Updates will also be shared by text and email through PublicInput.com and through Nextdoor social media app.
Construction activities expected to begin Fall 2026.
Potential update topics may include:
- Utility relocation activities
- Earthwork and grading operations
- Drainage installation
- Roadway construction
- Traffic control changes
- Pedestrian and bicycle accommodations
- Schedule milestones
Construction schedules may change due to weather, field conditions, utility coordination, permitting requirements, or other operational factors.
Traffic and Access Information
As construction progresses, temporary traffic pattern changes may be necessary to safely complete the work. Traffic and access updates will be shared by email and/or text through PublicInput.com and through Nextdoor as information becomes available and is confirmed.
Potential topics may include:
- Lane closures and lane shifts
- Temporary traffic pattern changes
- Intersection impacts
- Sidewalk or multi-use path impacts
- Access modifications
- Detour information
- Night or weekend work notices
Travelers, nearby residents, and businesses are encouraged to sign up through PublicInput.com to receive traffic and access updates by email and text message, check this page regularly for the latest verified project information, and watch for project notifications shared through Nextdoor when appropriate.
Project Map
View or Download PDF of Project Map
Click on the image below to open the map in a new window
History
The Strategic Transportation Investments (STI) law includes a provision for a funding allocation to local governments based on funding contributed by the local government to transportation projects or revenue from tolling. This bonus allocation can be used to fund the construction of other eligible highway projects.
Early in 2020, the Capital Area Metropolitan Planning Organization (CAMPO) received notice from NCDOT that there would be a bonus allocation to CAMPO from the N.C. 540 (toll road) project. This project, on Sunset Lake Road, was one of several selected by CAMPO for the bonus allocation funding. NCDOT began project development work for the project in early 2021.
Project Funding
| Estimated Amount* |
| Project Development / Design | $ 250,000 |
| Property Acquisition | $ 630,000 |
| Construction | $ 3,700,000 |
| Total Cost | $ 4,580,000 |
* Estimated costs are subject to change. Based on NCDOT STIP.
Project Timeline
Milestone | Date* |
| Right of Way Acquisition | January 2024 |
| Construction to begin | Fall 2026 |
| Substantial completion | Spring 2027 |
| Completion of Vegetation | Winter 2027 |
* Future dates are preliminary and subject to change
PROJECT CONTACT INFORMATION
Zahid Baloch, PE
Senior Project Engineer
NCDOT Highway Division 5
1573 Mail Service Center
Raleigh, NC 27699-1573
PROJECT CONTACT INFORMATION
Jay McInnis, PE
Consultant Project Manager
Ramey Kemp Associates
5808 Faringdon Place
Raleigh, NC 27609
Frequently Asked Questions
Widening Sunset Lake Road to four lanes with a median between Holly Springs Road and Lockley Road. A sidewalk is planned on the west side and a multi-use path will be built on the east side of Sunset Lake Road within the project limits.
Traffic impacts may occur throughout construction. Advance notice will be provided when major traffic pattern changes, lane closures, or access modifications are planned and confirmed.
One extended closure is expected to last 59 hours over a weekend as crews install roadway drainage. Sunset Lake Road will close between Eisenhower Drive and Holly Springs Road.
The closure is scheduled to begin at 7 p.m. Friday and end at 6 a.m. Monday.
During the closure, drivers will be detoured along Holly Springs Road, North Main Street (N.C. 55) and Sunset Lake Road.
NCDOT and project partners are coordinating on activities that could affect school transportation, crossings, and campus access with Wake County Public Schools.
NCDOT is responsible for managing the highway project and providing verified information about construction activities, traffic control, and project scheduling.
Residents, businesses, and travelers are encouraged to sign up through PublicInput.com to receive project updates by email or text message and to monitor this page, which serves as the official source for verified project information. Project notifications may also be shared through Nextdoor to help reach nearby communities.
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos
Page last updated: September 29, 2026