U-6107: U.S. 17 Intersection Improvements

U-6107: U.S. 17 Intersection Improvements

 

The NC Department of Transportation is proposing to improve intersection on U.S. 17 at McDaniel Drive / Workshop Lane in Onslow County. 

There are two alternatives under consideration for this project:

  • Option 1 proposes conventional intersection improvements to the intersection of U.S. 17 and McDaniel Drive/Workshop Lane, including construction of additional driving lanes and alterations to existing medians

  • Option 2 proposes converting the intersection of U.S. 17 and McDaniel Drive/Workshop Lane to a superstreet by installing concrete islands at the median in the current intersection and constructing U-turn bulbs at the intersections of U.S. 17 and Parkwood Drive and U.S. 17 and Fairway Road.  

 

Vicinity Map:

 

Purpose and Need:

STIP project U-6107 will make intersection improvements to the intersection of U.S. 17 and McDaniel Drive/Workshop Lane in the city of Jacksonville in Onslow County, NC.

 

The purpose for this project is to decrease wait times and improve traffic flow and safety at this intersection.

 

 

Public Involvement

Public Meetings

A public meeting will be held on June 3, 2019 in Jacksonville, NC to obtain stakeholder and public input regarding the project's design.  

 

  Date:

  June 3, 2019

  Location:

  Jacksonville Department of Public Safety (Community Training Room)

200 Marine Blvd, Jacksonville, NC 28540

  Time:

  5-7 p.m.

                                                    

                          

Public Meeting Maps:

U.S. 17 at McDaniel Drive/Workshop Lane Alternative 1 map

 

U.S. 17 at McDaniel Drive/Workshop Lane Alternative 2 Map

 

 

Project Funding

 This project is listed as Project U-6107 in the N.C. Department of Transportation’s State Transportation Improvement Program  (STIP) and is funded for $1.54 million.

 

 

 Estimated Amount*

   Property Acquisition   $          400,00     
   Construction   $    1,140,000     
   Total Cost   $    1,540,000     

* Estimated costs are subject to change. Based on NCDOT STIP.

 

Project Timeline

 Milestone

    Date*

  Public Meeting 

     June / 2019

  Right of Way Acquisition 

     November / 2020

  Construction Begins

     August / 2023

* Future dates are preliminary and subject to change

PROJECT CONTACT INFORMATION 

Michael Bass

Engineer Technician

NCDOT Division Highway 3

5501 Barbados Blvd.

Castle Hayne, NC  28429

[email protected]

         910-341-2000

PROJECT CONTACT INFORMATION 

Tommy Register

Consultant Project Manager

TGS Engineer

706 Hillsborough Street, Suite 200

Raleigh, NC  27603

[email protected]

        919-773-8887

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

 

Relocation Assistance Brochure                                       Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure             Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Would you like to be added to the project email list?
Do you have a comment you want to submit to the project team.