U-5825: Ten-Ten Road (Apex and Cary)
U-5825: Ten-Ten Road (Apex and Cary)
PROJECT DESCRIPTION
NCDOT is proposing to widen Ten-Ten Road from Apex Peakway in Apex to Kildaire Farm Road in Cary. The primary need for this project is to address delay and congestion currently present along the corridor.
The project team is currently developing alternatives to address the congestion issues facing this corridor. Current efforts include evaluating alternatives such as conventional widening and superstreet configurations. Some sections are expected to be widened to four through lanes, while others may warrant a wider, six-lane cross section.
The project will also replace the existing Ten-Ten Road bridge over U.S. 1 with a new, wider bridge to accommodate future traffic. The bridge is also expected to include pedestrian and bicycle facilities, such as a mixed-use path, sidewalk, and/or an exclusive on-road bike lane.
This project will be reprioritized for funding in the next State Transportation Improvement Program. A schedule for right of way, utilities and/or construction has not been finalized at this time. However, preliminary engineering activities (design, planning, studies) needed for project development are underway.
Vicinity Map:
Interactive Vicinity Map
ABOUT THE PROJECT
NCDOT began a study to improve Ten-Ten Road from Apex Peakway in Apex to Kildaire Farm Road in Cary in mid-2016. Prior to the start of this planning and design effort, this corridor was identified for widening in the currently adopted Capital Area Metropolitan Planning Organization’s (CAMPO) 2040 Metropolitan Transportation Plan (MTP). The corridor was also identified in local municipal plans for the Towns of Apex and Cary.
Town of Apex Comprehensive Transportation Plan (2011)
Town of Cary 2040 Community Plan (2017)
The project team has begun a number of technical environmental studies, including a Natural Resources Report and Community Studies report, as well as development of functional designs for two alternatives.
ESTIMATED COSTS
Activity | Estimated Cost* |
Right of Way Acquisition | $ 26.8 Million |
Utility Costs | $ 4.7 Million |
Construction Costs | $ 63.9 Million |
Total Cost | $ 95.4 Million |
* Estimated Costs as shown in Current 2018-2027 STIP and are subject to change
TIMELINE
Milestone | Date* |
---|---|
Public Meeting #1 | Spring 2018 |
Public Meeting #2 | Summer 2018 |
Environmental Document Complete | June 2019 |
Right of Way Acquisition | July 2032 |
Construction Begins | Spring 2040 |
*Future dates subject to change
PUBLIC INVOLVEMENT
The NCDOT project team will review all feedback – regardless of how it is submitted (online, phone, email, or letter) – and explore options to incorporate comments and address concerns where and when feasible.
PUBLIC MEETINGS
NCDOT held two open-house public meetings during 2018. At each of these meetings, staff were available to discuss the alternatives and answer questions.
Public Meeting #1 was held on March 1, 2018 at The Summit Church located at 300 Lufkin Road in Apex. The meeting was an open-house style public meeting from 4 to 7 P.M.
Public Meeting #2 was held on October 23, 2018.
Persons who do not speak English, or have a limited ability to read, speak or understand English, may receive interpretive services upon request prior to any meeting by calling 1-800-481-6494.
Aquellas personas que no hablan inglés, o tienen limitaciones para leer, hablar o entender inglés, podrían recibir servicios de interpretación si los solicitan antes de la reunión llamando al 1-800-481-6494.
PUBLIC MEETING MAPS
Maps for Public Meeting - October 23, 2018
Conventional Widening - Sheet 1
Conventional Widening - Sheet 2
______________________________________________________________________
Maps and Documents from First Public Meeting - March, 2018
Conventional Widening - Map 1 (Western Side)
Conventional Widening - Map 2 (Eastern Side)
Superstreet Widening - Map 1 (Western Side)
Superstreet Widening - Map 1 (Eastern Side)
Responses to Groves Neighborhood Comments Received
Responses to Comments Received
TECHNICAL DOCUMENTS
COMMENTS/QUESTIONS
Comments may be submitted via phone, email or U.S. Mail to either of the individuals listed below or at any meeting. All comments received carry equal weight, regardless of submittal method. All comments will be reviewed and suggestions/recommendations incorporated into designs where feasible.
PROJECT CONTACT INFORMATION
John Braxton |
NCDOT Project Manager |
Highway Division 5 - Project Delivery |
1573 Mail Service Center |
Raleigh, NC 27699-1582 |
919-707-6219 |
jwbraxton@ncdot.gov |
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos