FS-1501A: U.S. 17/Future I-87 - Feasibility Study

PROJECT DESCRIPTION

Feasibility Study of upgrading U.S. 17 beteen Williamston and the Virginia State Line to interstate standards.  

A feasibility study is a preliminary analysis document.  It is the initial step in the planning process for a Transportation Improvement Program (TIP) project.

It does not do exhaustive human and natural environmental analysis, nor does it provide detailed designs and there is also no extensive public or stakeholder involvement.   

What is a Feasibility Study? 

A study undertaken to:

  • identify the needs for the project
  • describe the proposed project
  • develop initial alternatives that could address the needs for the project
  • identify preliminary costs 
  • identify potential impacts
  • identfy and potential problems that may require consideration in teh planning and design phases

A feasibility does not determine the alternative to be constructed.

 

Vicinity Map    

 

Interactive Map :  https://goo.gl/nKf87j 

 

PROJECT HIGHLIGHTS

U.S.17 is the only north-south corridor east of I-95.  It stretches 284 miles from South Carolina to Virginia and serves 13 North Carolina Counties.  55 miles of the roadway are categorized as freeway, 155 miles are expressway/multilane and 75 miles are two-lane highways. speed Limits range from 45 mph to 70 mph. Approximately 79.5 miles lie within this feasibility study's area between Martin County and the Virginia State Line.  It passes through 6 North Carolina counties, Martin, Bertie, Chowan, Perquimans, Pasquotank and Camden.  One Segment explored would extend into Currituck County. The purpose of the project being evaluated This being to Upgrade U.S. 13/17 from U.S. 64 in Williamston to Virginia to interstate standards to improve mobility, connectivity, and safety.

PROJECT HISTORY

In 2015 both houses of Congress passed federal transportation legislation authorizing a future Interstate designation for the full corridor between Raleigh and southeastern Virginia via northeastern North Carolina.  The corridor received the I-87 designation in May 2016.  

Interesting Historical Facts about the I-87 Designation

The number 87 is an appropriate tribute to the rich histories of the North Carolina and Virginia. 

  • 1587, the Roanoke Colony founded by Sir Walter Raleigh was established in what is now Dare County, North Carolina.
  • Also in 1587,  Virginia Dare was born in the colony, becoming the first child of English parents born in America. 
  • In 1787, the James Madison’s Virginia Plan for the nation’s new government was presented at the Constitutional Convention by Virginia delegate Edmund Randolph.  This document proposed the bicameral Congress that exists today.  
  • In 1887, North Carolina State University, now the largest in the Carolinas, was founded in Raleigh, the location of the southern terminus of I-87.

On December 4, 2015, President Obama signed into law the Fixing America's Surface Transportation Act (FAST Act) .  This law provides long-term funding certainty for surface transportation.  This means that state and local goverments can move forward with critical transportation projects such as new highways and transit lines with the confidence that they will have a Federal partner over the long term.  The FAST Act designates three high-priority corridors in eastern North Carolina:  U.S. 17, U.S. 70 and U.S. 117/I-795.

TYPICAL SECTION

Typical Right of Way width would be 300 feet, with tow 12-foot lanes in each dirction, a 10-foot outside shoulder, 4-foot  inside shoulder and a 46-foot minimum grass median (70 foot desired) between directions.  The posted speed would be 70 mph and there would be full control of access.  This means that no driveways would be allowed along the corridor. 

MAPS

The following maps are conceptual designs only.  There are 10 main sections for the project corridor.  Most sections have multiple pages (one click and leaf through pdf pages) and some have multiple options (shown as "A" or "B").  The map below shows where these overall sections are located for ease of viewing.  

Click on a Section below to view - be patient - many are multiple pages.

Section 1

Section 6

      Section 1A

Section 7

      Section 1B

      Section 7A

Section 2

Section 8

Section 3

Section 9

      Section 3A

Section 10

Section 4

      Section 10A

Section 5

 

      Section 5A

 

NEXT STEPS

  • The Feasibility Study Report will be circulated for review and comment.
  • The project sections will be submittted for the Prioritization Process 
  • Obtain ranking in the State Transportation Improvement Program 

PROJECT CONTACT INFORMATION

 

Shane York, PE Christy Shumate, AICP
Project Engineer NCDOT Consultant
NCDOT Feasibility Studies Unit AECOM
1534 Mail Service Center 701 Corporate Center Dr
Raleigh, NC  27699-1534 Raleigh, NC  27607
[email protected] christy.shumate@aecom.com

 

Comments 

Comments may be submitted by mail or email to either of the project contacts shown or they may be submitted by completing the comment block at the bottom of this page.

Other Studies and Strategies Associated with U.S. 17 and Important to this Study

N.C. Maritime Strategy 

In 2012, Initiated by the Governor’s Logistics Task Force (GLTF), the North Carolina Maritime Strategy took a  look at North Carolina’s maritime assets and the needs for improvement to ensure that our State remains competitive in the future.  That Task Force found that Highway Improvements would lead to potential travel time savings and lower delivery costs for North Carolina Shippers.  According to the N.C. Multimodal Freight Plan, Maritums Study, $1.05 million of waterborne agrivulture exports from N.C. depart from Virginia, $173 million pass through South Carolina and $101 million through Georgia.  N.C. is a top destination for imports handled by the Port of Norfolk.  

The Port of Virginia submitted an application as a result of this Task Force's findings to expand their Foreign Trade Zone to include Currituck, Camden, Chowan, Pasquotank and Perquimans county.  This designations provides industries in the area with benefits that encourage them to establish and maintain operations.  

2013 Ecomonic Impact Study

In 2013 an Economic Impact Study found a number of benefits for the project including: 

  • Clear value that continued  public investment in making US 17 a safer, less congested, higher-speed facility
  • In keeping  with the region’s economic development and economic opportunity goals
  • Would increase economic opportunities for agri-business and tourism, and enhance safety and logistics 
  • Jobs would be created in each of those sectors, as well as in the construction industry 

Would continue to:?

  • provide opportunities to divert traffic off of Interstate 95
  • enhance industrial development activity
  • increase retail activity, 
  • reduce travel time, 
  • improve traveler safety, 
Governor's 25 Year Vision for N.C.
 
In 2014, Governor Pat McCrory unveiled his vision plan which involved developing infrastructure solutions for N.C.  The eastern forcus included improving the highway to Hampton roads, strengthening military connections and enhancing freight movement as well as connections to I-95.  
 

Strategic Transportation Corridor Policy

The stated purpose of Strategic Transportation Corridors is to identify from existing facilities a network of multimodal high priority strategic transportation corridors which will form the state’s core network of highly performing facilities for movement of high volumes of people and freight. The facilities and services in those corridors are considered to be of great importance on a statewide basis for long-distance movement of people and freight. The policy establishes that preservation of those facilities at a consistently high level of functionality, in terms of classification, condition, and service, will guide long-term planning at statewide, regional, and corridor levels and should be considered the state’s highest priority when such corridors are being analyzed within the framework of regional or local transportation and land use plans. 

The goal of the Strategic Transportation Corridor policy is to have an identified network or high-priority, multimodal transportation corridors that connect statewide and regional transportation-dependent activity centers to enhance economic development, reliable and efficient mobility and accessibility, and good decision-making

 

NCDOT Resources for Property Owners


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

 

Relocation Assistance Brochure                                                 Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure                             Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

NCDOT Poll:
Are there questions you have or comments you wish to make? (please remember to provide an email or USPS address if you would like a response or to be added to our project mailing list.)